Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In
Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?
A、P
B、Q
C、R
D、S
E、T
【答案】A