Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In

Using the data shown in the Special window, Activities P, Q, and T are critical path activities. In order to shorten the time duration of the project, which activity should be "crashed" first?

A、P

B、Q

C、R

D、S

E、T

【答案】

A